The Buildings, Safety Engineering, and Environmental Department (BSEED) is the City of Detroit's authority for building permits, trade permits, construction inspections, zoning, and contractor licensing. If you're building, rehabbing, or doing trade work inside Detroit city limits, BSEED is the department that approves your plans, issues your permits, signs off on your work, and hands you your Certificate of Occupancy.
BSEED is located at the Coleman A. Young Municipal Center (CAYMC), 2 Woodward Avenue, Detroit. Permit applications go through the eLAPS online portal at permits.detroitmi.gov.
Building permits cover new construction, additions, renovations, and changes of occupancy. Plans are submitted and reviewed online through BSEED's plan review systems before a permit is issued.
Before submitting, use BSEED's Preliminary Plan Review (PPR) meeting to align with City departments early — especially on complex projects. PPR is available through the Development Resource Center. If you have building or trade code questions mid-design, request a Pre-Plan Consultation instead.
BSEED issues trade permits across six disciplines:
Trade permits are pulled separately from building permits. Know which trades your scope requires before you submit — each has its own registration and inspection requirements.
BSEED has streamlined fire alarm permitting to eliminate duplicate review. If the Detroit Fire Marshal has issued a fire alarm permit, you no longer need a separate BSEED building permit for the fire alarm system. The Fire Marshal's inspection also satisfies testing and certification requirements.
Trade permits (electrical, mechanical) are still required for any associated installation work.
All permit applications go through eLAPS (Electronic Licensing and Permit System) at permits.detroitmi.gov. You can scope your project, verify zoning, and estimate permit fees using the online tool before submitting.
BSEED's Construction Inspection Division performs all inspections on active construction projects in Detroit. Inspectors verify that work matches approved plans and meets code before signing off.
Schedule online or call BSEED at (313) 224-3202. Inspect by trade — each of the six trade teams has its own supervisor.
| Trade | Supervisor | Contact |
|---|---|---|
| Boilers | Aijalon Denham | [email protected] / (313) 628-2433 |
| Buildings | Jerrid Pernell | [email protected] / (313) 628-2458 |
| Electrical | Rickey Harris | [email protected] / (313) 224-3113 |
| Elevators | Ricardo Knott | [email protected] / (313) 224-9401 |
| Mechanical | Clarence Burnett | [email protected] / (313) 224-3189 |
| Plumbing | Ross Brackett | [email protected] / (313) 224-3157 |
Chief of Construction Inspection: Randy Hargraves — (313) 224-9102
General inquiries: [email protected]
A Certificate of Acceptance (C of A) confirms that completed trade or building work passed inspection and meets current codes. It's required for permit closeout on alterations and repairs.
Process:
If a contractor completed the work, the property owner may receive the C of A if the contractor authorizes it in a certified letter.
A Certificate of Occupancy (C of O) is required before a new building or a change-of-occupancy space can be occupied. It confirms all work is approved and the building is safe for use.
Process:
BSEED's Zoning Division handles site plan reviews, Conditional Land Use hearings, and zoning verification. Before starting a project, confirm your proposed use is allowed in the property's zoning district using BSEED's online mapping tool at permits.detroitmi.gov.
If your project requires Site Plan Review, apply online and include the Site Plan Review Checklist. Zoning questions can also be addressed through a PPR meeting or Pre-Plan Consultation.
To pull permits in Detroit, contractors must be licensed and registered with the City. Requirements vary by trade:
Determine the license type required, then complete the registration and renewal form through BSEED. For engineering and boiler licensing questions: (313) 224-3184. For elevator licensing: (313) 224-9401.
The Development Resource Center (DRC) is BSEED's front door for contractors and developers navigating permitting and zoning. Use the DRC to:
Book a DRC meeting at permits.detroitmi.gov or use the Project Facilitator Request Form on the DRC page.
Source: City of Detroit Buildings, Safety Engineering, and Environmental Department — detroitmi.gov/bseed