The Great Lakes Water Authority (GLWA) is the regional utility that owns and operates the water and sewer transmission infrastructure serving Detroit and 127 surrounding communities across southeast Michigan. Any contractor doing utility construction — water main, sanitary sewer, wastewater, or related civil work — on a GLWA or DWSD project will interact with GLWA's contracts, standards, and procurement system.
This article covers what a contractor needs to know: who GLWA is, what they build, how their specifications work, how contractors get paid, and how to get in front of their solicitations.
GLWA was created in 2016 when the City of Detroit restructured the Detroit Water and Sewerage Department (DWSD) into two separate entities. GLWA took over the regional wholesale and transmission infrastructure. DWSD retained the local Detroit distribution and collection system.
The practical difference for contractors:
GLWA's service area covers roughly 3.8 million people. It is one of the largest water and wastewater systems in the United States.
GLWA operates five water treatment facilities drawing from Lake Huron and the Detroit River. The system includes major transmission mains, pumping stations, and storage reservoirs that feed local distribution systems operated by member partners.
GLWA maintains an active Capital Improvement Plan (CIP), updated annually, that identifies multi-year infrastructure investments. The CIP is where construction contract opportunities originate — new water main, pump station rehabs, treatment plant upgrades, and facility work. GLWA publishes its current and historical CIP at glwater.org/CIP.
GLWA's Water Resource Recovery Facility (WRRF) in Detroit is the largest single-site wastewater treatment facility in North America. It serves 76 communities and processes hundreds of millions of gallons per day. Interceptor sewers, pump stations, and combined sewer overflow infrastructure throughout the region round out the wastewater system.
The GLWA Master Specifications (Version 2.1) is the governing construction specification library for all GLWA projects. It spans 3,586 pages across five volumes and 17 divisions organized under the CSI MasterFormat standard.
| Division | Scope |
|---|---|
| Division 1 — General Requirements | Administrative provisions, payment, scheduling, submittals, QC, closeout |
| Division 2 — Site Construction | Trenching, backfill, sewers, manholes, water main, hydrants, erosion control |
| Divisions 3–10 — Structural/Building | Concrete, masonry, metals, doors, finishes |
| Divisions 11–14 — Equipment | Process equipment, mechanical systems |
| Division 15 — Mechanical | Ductile iron and steel pipe, valves, gates, HVAC, odor control |
| Division 16 — Electrical | Drives, motors, switchgear |
| Division 17 — Instrumentation | SCADA, telemetry, process controls |
For specialty trade contractors, Division 2 (site work) and Division 15 (mechanical/piping) are the highest-impact sections.
Project contract documents call out spec sections by number. A water main rehabilitation bid might reference 02221 (Trenching, Backfilling and Compacting), 02620 (Water Main Services), and 15061 (Ductile Iron Pipe). Each section follows the same three-part structure: General, Products, Execution.
The specs are not modified for individual projects. When a project has site-specific conditions that differ from the Master Spec, the design engineer issues a Provisional Specification. Provisional specs govern whenever there's a conflict — always read them first in the project documents.
GLWA maintains the official, current version at glwa.org. The November 2017 V2.1 release is the baseline, with supplemental specifications posted separately.
Payment on GLWA contracts runs on a 30-day cycle. Each month, the contractor submits a Progress Schedule Submittal package with three components:
The initial schedule (Rev 0) is due five days after the second payment period closes. The Detailed Cost Breakdown is due separately within 10 days of Notice to Proceed. Rev 0 sets the baseline — delays in getting it accepted directly compress early billing.
Progress meetings occur monthly within five working days of the payment cut-off date. The contractor must bring a 3-week look-ahead schedule in bar chart format and a written narrative on construction status. These are contractual deliverables, not optional updates.
GLWA contracts use these payment structures:
Submittals come in two types.
Administrative submittals (due early, before construction proceeds):
Technical submittals (specific to the work):
You cannot fabricate, procure, or install anything until the relevant technical submittal has been reviewed and approved by the Engineer. Ordering materials before approval is at your risk — any resulting costs are yours.
The contractor is responsible for a formal QC program meeting ISO 9000 and 9001 standards. The QC Plan must be submitted at least 14 days before the pre-construction QC coordination meeting. No separate payment is made for QC — the cost is embedded in your lump sum and unit prices.
Shutdown protocol: Any work requiring an operational shutdown of existing facilities requires a written inventory of labor and materials submitted 30 days in advance, followed by a written shutdown approval request 14 days before the proposed date. No shutdown starts without the Engineer verifying all materials are on-site.
Warranties apply to all work, even where not explicitly called out in a spec section.
GLWA uses Euna Procurement (formerly Bonfire) for all public solicitations. Registration is required to bid on any GLWA contract.
Steps to get in front of GLWA work:
GLWA publishes an annual procurement report and a full searchable contract database through the portal. GLWA's FY2025 Annual Procurement Report is available at glwater.org/vendors.
GLWA contracts carry significant administrative load. CPM scheduling, monthly submittals, QC plans, and warranty binders are contractual deliverables — not paperwork you do when you have time. They gate your ability to bill, and deficiencies compound fast.
Contractors who treat documentation as separate from field operations consistently underperform on GLWA projects — at pay app review, at progress meetings, and at closeout. The specs assume you have systems in place. If you don't, the gap becomes visible quickly.